Pristina Deputy Mayor Besianë Musmurati held a press conference at which she outlined the timeline of the project to modernize the capital’s waste collection and management system, stating that the project remains unimplemented because the Ministry of Finance has not signed the agreement, reports Ekonomia Online.
Musmurati: MF is blocking the €74 million project to clean Pristina; 100 trucks and 10,000 containers are waiting
Musmurati said that the Regional Cleaning Company’s current capacity is severely damaged, and stressed that the project, financed through the German Development Bank (KfW), envisages the purchase of 100 new trucks, 10,000 containers and other infrastructure investments to improve cleaning services.
She said the project began more than three years ago and that, according to her, despite negotiations, agreements and institutional decisions, the Ministry of Finance has still not completed the loan-signing process.
“Today I want to address the citizens of Pristina. Seeing the alarming situation with waste in Pristina, I want to explain to the public that the Regional Cleaning Company’s current waste collection capacity is severely damaged. I know the reason; the following presentation we want to make here will show the three-year wait by the Cleaning Company to purchase 100 new trucks, 10,000 containers, and, through a loan of €74 million from the German Development Bank, which is not being signed.”, Musmurati said.
She said that at the press conference she would present documents and facts dating back to 2023, in order to show the project’s progress and the institutional responsibilities involved in the process.
“To be accurate and show the actual situation in relation to the German Development Bank, I will present all the facts about this project, which is failing because the Ministry of Finance is not signing it. Therefore, I also ask for your understanding as I present the documents and facts from 2023 to the present day. Here, as you can see, we have a timeline of dates with meetings, negotiations, government decisions and agreements between all parties to begin implementing the project. But we need to start from the beginning, because it is important for citizens to understand that this project did not start yesterday,” she said.
According to Musmurati, the first contacts about the project began in May 2023, when the first meeting was held between the Cleaning Company and the German Development Bank (KfW). Then, in October of that year, meetings were held with the relevant institutions, including the Ministry of Finance, and preparation of the project began.
“Back in May 2023, when the first meeting between the Cleaning Company and Germany’s KfW took place, meetings were held with all the institutions in October of that same year, including the Ministry of Finance, and preparation began for this extremely important project for the capital and the entire Pristina region. So, we are talking about an institutional process that began more than three years ago.”
During her presentation, Musmurati explained that the project was divided into two phases. The first phase provides for a €4.1 million grant from the German government and a €20 million soft loan, while the second phase includes €50 million in investments.
“And what does this project provide for? The project is divided into two forces: the first force provides for a €4.1 million grant from the German government to the Government of Kosovo to engage initial consultants to start the project, as well as a €20 million soft loan to purchase 100 new trucks, 10,000 new containers, container platforms worth €1 million, and other consultancy services. And the second phase, as you can see here, includes investments of €50 million to acquire even more trucks as needed, even more containers as needed, and to establish a waste recycling and composting center,” she stressed.
She also presented the first agreement reached in October 2023, which, according to her, was signed by the mayors of the municipalities in the Pristina region, the relevant ministers, the Cleaning Company and the German Development Bank.
“What you see here is the first agreement for the German KfW projects, reached in October 2023. It provided for the first phase of the project, in which the German government offered €4.1 million, as I said earlier, and a €20 million soft loan. As you can see here, this agreement was signed by everyone, that is, the mayors of the municipalities in the Pristina region, including the Mayor of Pristina, Minister Hekuran Murati, the Minister of Environment, the Cleaning Company, as well as the German Development Bank. So, the initial agreement to launch this project was reached in October 2023,” Musmurati said.
Musmurati also explained the financial terms of the €20 million soft loan, noting that it had a maturity of 38 years, a six-year grace period and an interest rate of 0.75 percent.
“The soft loan, which amounted to €20 million, had a maturity of 38 years, a six-year grace period and an interest rate of 0.75%. So, we are talking about an extremely favorable loan for the Republic of Kosovo,” she said.
According to the timeline presented by the Pristina deputy mayor, official bilateral negotiations between the Government of Kosovo and the German government began on April 30, 2024. The Pristina cleaning project was included in these negotiations.
“And what happened on April 30, 2024? On April 30, 2024, official bilateral negotiations began between the Government of Kosovo and the German government. The project to clean Pristina was also part of these negotiations, and the launch of this extremely important project was envisaged. You also have part of the agenda here, showing that the participants included the Ministry of Finance, the German Development Bank, the Municipality of Pristina and other extremely important stakeholders,” she said.
She said that on September 10, 2024, the Ministry of Finance was notified that the German government had approved the project, worth €24.1 million for the first phase and €50 million for the second phase. Then, on September 26, 2024, the German government sent the draft grant and soft-loan agreements to the Government of Kosovo.
“Then, naturally, after the negotiation process between the two governments was completed, on September 10, 2024, the Ministry of Finance was notified that the German government had approved the project worth €24.1 million and €50 million for the second phase. On September 26, 2024, the German government sent the draft grant and soft-loan agreements to the Government of Kosovo. So, since September 2024, Hekuran Murati has had the loan agreement on his desk to implement this project to clean Pristina,” she said.
One of the documents Musmurati highlighted during the press conference was the Kosovo Government decision dated December 18, 2024, which approved the initiative for a loan agreement with KfW and the Cleaning Company.
“Another very important thing is that December 18, 2024, is also an important date. As you can see, this is a public document: the government approves the initiative for a loan agreement with KfW and the Cleaning Company. The decision is numbered 17/238 and was signed by Prime Minister Albin Kurti himself. So, you can see here that it is a government decision. What is extremely important about this decision is that Albin Kurti himself obliges Hekuran Murati to implement this project,” she stressed.
According to her, despite this decision and the prepared documentation, the agreement has not been signed by the Ministry of Finance.
“From December 18, 2024, until March 2026, the KfW documentation continued to await the finalization of the agreement. The loan agreement was still listed as an agreement on paper and an agreement awaiting signature by the Ministry of Finance,” she said.