The Minister of Economic Development, Blerand Stavileci, announces that commercial agreements with the American investor “Contour Global” will be signed in March. This will pave the way for the tendering process to select the builder of the “Kosova e Re” power plant. The process will be completed by the end of this year, and construction is expected to begin in 2018. The “ […]
Stavileci: “Kosova e Re” to begin in 2018; we are creating a century-long solution

The Minister of Economic Development, Blerand Stavileci, announces that commercial agreements with the American investor “Contour Global” will be signed in March. This will pave the way for the tendering process to select the builder of the “Kosova e Re” power plant. The process will be completed by the end of this year, and construction is expected to begin in 2018.
The “Kosova e Re” power plant will have a generating capacity of 450 megawatts. The financial value of the project is estimated at around one billion euros.
Minister Stavileci tells Ekonomia Online in an interview that “Kosova e Re” will provide a century-long solution. “Construction takes four years, and starting around 2022, when this new capacity is installed and operational, I believe we will finally achieve what I call a century-long solution, because we will no longer have problems with a regular supply of electricity,” he says.
Several civil society organizations have opposed the construction of the “Kosova e Re” power plant, warning of higher electricity prices as well as pollution problems.
However, the head of the Ministry of Economic Development emphasizes that coal is one of Kosovo’s main resources and that new generating capacity should have been built by making use of this underground resource. On the other hand, he assures that the technology to be used at this power plant will be modern and environmentally friendly. “I believe the environment is polluted more by cars than it will be by this power plant.”
Stavileci also stresses the importance of Kosovo becoming independent in the energy sector, and in a way compares those who oppose the construction of “Kosova e Re” to opponents of the country’s independence.
FULL INTERVIEW:

EO: Minister, when exactly will construction of the “Kosova e Re” power plant begin, and when are the citizens of the country expected to receive electricity from this power plant?
Stavileci: As we have said in the past, we are very close to finalizing all the final stages needed to begin construction of the power plant, but naturally it cannot start immediately tomorrow, before some further processes are completed. To be more precise about the timeframe when I say we are very close, next month we will sign the commercial agreements. This will pave the way for the investor to tender for the builder of the power plant, which is expected to take place within a period of 3–4 months, after which the financial close will be completed. Therefore, I think this entire process will be completed by the end of this year, and construction should begin next year.
The public should be informed, although we have said this before, that construction will take four years, and starting around 2022, when this new capacity is installed and operational, I believe we will finally achieve what I call a century-long solution, because we will no longer have problems with a regular supply of electricity.
It should be said that this is not the only project; we have other projects that we are developing so that all the citizens of Kosovo can have a regular, sustainable and high-quality electricity supply.
EO: It has been said that “Kosova A” will close once the “Kosova e Re” power plant begins operating. Will the country risk not having enough electricity, and what will happen to the workers who worked at the “Kosova A” power plant?
Stavileci: “Kosova e Re,” “Kosova A” and “B” are all part of a package that we have translated into the objectives of our program and the 2017–2026 energy strategy. To ensure a regular electricity supply, we need to build new capacity, but also regenerate existing capacity. “Kosova e Re” will be part of the new capacity, while “Kosova B” will be part of the regeneration of existing capacity. We have said that the fate of “Kosova A” will be closely linked to that of “Kosova e Re.” Naturally, there will be a need for a workforce, both the existing one and new staff, because especially at “Kosova e Re” the work will involve highly advanced technology, and staff with various professional profiles will be needed to manage and operate the power plant. Naturally, in addition to this objective, from 2022 onward we will no longer have the problems that have affected us for almost two decades. We will be very careful not to cause any kind of crisis at any point, because while “Kosova e Re” is being built and “Kosova B” begins to be rehabilitated, we are working with everyone to coordinate the timing: when one is being built, there must be sufficient capacity; when the other is being rehabilitated, there must be other capacities, so to speak, in reserve to make up for that amount. But until “Kosova e Re” is completed, unfortunately we need to import, and we will import. We believe that from 2022 onward we will be self-sufficient. And when a common market with Albania and a common regional electricity market are established, I think that we, especially together with Albania, will be one of the regional powers in terms of electricity.
EO: Civil society and other actors have opposed the “Kosova e Re” project, even saying that construction of this power plant will cost Kosovo dearly, with electricity prices rising to levels citizens cannot afford. How do you respond to these criticisms?
Stavileci: We have spent all these years talking about our country’s independence, which makes us proud. We see that there are still political problems with some neighbors, and those who side with our neighbors in an anti-Albanian policy and against an independent Kosovo. Perhaps less has been said about independence and sovereignty in other fields. The energy sector is the one that gives a country’s independence and sovereignty the most color and weight. Therefore, a truly independent state cannot exist without energy independence. I would not want to place those who oppose it among the opponents of independence, but one way or another, we are doing a kind of service to those who oppose independence. I understand some of the concerns they raise; we have discussed them several times. Although we are at the head of this important department, knowing that coal is one of our main resources and assets, we will not do anything that goes against environmental rules and standards. On the contrary, the technology to be used will be environmentally friendly, and I believe the environment is polluted more by cars than it will be by this power plant.
And secondly, we will not be deterred from our path. You can see even today that this investment is part of what we are jointly raising as an issue, and I think we are on the same wavelength as civil society here: alongside these investments, we will also launch investments in renewable energy and implement energy-efficiency measures.