LDK MP Avdullah Hoti has reacted to the 2027 budget for capital investments. In a post on his profile on the social network Facabook, Hoti wrote that the high budget figures are being used only for boasting when the budget is approved in the Assembly. “Over the past six years, implementation […]
Hoti criticizes the Kurti government: None of the capital projects have been completed

LDK MP Avdullah Hoti has reacted to the 2027 budget for capital investments.
In a post on his profile on the social network Facabook, Hoti wrote that the high budget figures are being used only for boasting when the budget is approved in the Assembly.
“Over the past six years, the implementation of capital investments has been extremely low. None of the major capital projects inherited from previous governments and begun before 2021 has been completed, including the Gjilan highway, the road to Peja, the road to Mitrovica, the road to Podujeva, the Dollc-Gjakova road, the Prizren-Gjakova road, etc.,” he wrote.
According to him, we are all bearing the economic and social consequences of the failure to complete capital projects.
Full post:
This government is deceiving itself and the public with a large budget planned for capital investments. The high budget figures are being used only for boasting when the budget is approved in the Assembly. When it comes time to report to the Assembly on budget implementation, no member of the government appears before MPs and citizens to answer for the failures to complete projects.
Over the past six years, the implementation of capital investments has been extremely low. None of the major capital projects inherited from previous governments and begun before 2021 has been completed, including the Gjilan highway, the road to Peja, the road to Mitrovica, the road to Podujeva, the Dollc-Gjakova road, the Prizren-Gjakova road, etc.
The projects promised by this government have not been completed either, including the Prizren-Tetovo road and tunnel, the Pristina-Durrës railway, Gjakova Airport, childcare centers, social housing, dams for water storage, and other projects.
Therefore, no one believes any longer in the high capital investment figures envisaged in the 2027 budget.
Budget implementation for capital investments has remained low even though procurement procedures have in many cases been conducted through negotiations, as evidenced by hundreds and thousands of single-source or negotiated tenders.
We are all bearing the economic and social consequences of the failure to complete capital projects. The long queues on roads under construction for the past six years are costing everyone time and money. The failure to implement capital investments has left Kosovo’s economy without hundreds of millions of euros in circulation—funds that would have generated positive ripple effects in the economy.